WATERFRONT UPDATES
Port Union Village Common Park Improvement Project
1. The project has a revised final completion target date of end of June
2011, due to the final building location requiring revision, other
unforeseeable existing site conditions, and a required electrical
transformer shutdown that can only be done in warmer weather.
2. The foundation, concrete slab, interior walls and exterior wall work is
mainly completed.
3. The roofing framework material is on site and planned to be installed
by end of Mar 2011.
4. The contractor advises that the building shell completion date is end
of Mar 2011, except warm-weather dependent electrical, landscaping and
finishing work, to be done as soon as weather permits.
5. The final electrical service connection must be scheduled in Spring
2011, due to a required residential block temporary shut down by Toronto
Hydro.
|